Maryland Avenue Reconstruction

Contact us

Ramsey County is working to reconstruct Maryland Avenue from Clark to Edgerton Street. The project entails the replacement of the existing pavement, enhancements to drainage systems, and the upgrading of pedestrian facilities.

Construction for this project is scheduled for the year 2026. As part of our commitment to community involvement, multiple open houses will be organized to afford individuals the opportunity to share their comments.

Timeline

  • Preliminary design – Fall 2023 - 2024
  • Final design – 2025
  • Construction – 2026

Upcoming Project Open House

This open house includes a visual preference activity and a walk-through of project updates since the last open house.

Wednesday, November 20, 2024
From 4-6 p.m.

Arlington Hills Community Center
1200 Payne Avenue
St. Paul, MN 55130

Past Community Engagement

Project Area