Silver Lake Road Drainage Reconstruction

Contact us

Silver Lake Road at Woodcrest Drive

This drainage reconstruction project is located on Silver Lake Road at Woodcrest Drive in the City of Mounds View and will be completed in 2024.

We will be replacing 4-inch diameter drain tile with 2 feet by 2 feet mini culvert relocated 10 feet North at low point. This will include excavation, minor road reconstruction, and replacing metal handrail.

The project will not require a detour or a full road closure.

Silver Lake Road at Rice Creek

This drainage reconstruction project is located on Silver Lake Road at Rice Creek in the City of New Brighton and will be completed in 2024.

We will be replacing undermined storm water pipes and structures, which will include excavation, minor road reconstruction and extensive water protection.

The project will require a detour since a full road closure at the project location will be needed.

 

Silver Lake Road detour map