Arenas Energy Savings and Clean Energy Production Project

We are excited to announce a significant step toward sustainability and energy efficiency in our community. The County Board has approved a $6.6M energy project in partnership with Parks & Recreation and Honeywell Inc. This initiative will help reduce energy consumption, advance sustainability, and support the county’s climate equity action plan. This project will enhance our arenas and facilities through the installation of solar arrays, LED lighting upgrades, advanced building management systems, mechanical system upgrades and more. In addition, energy efficiency improvements will significantly reduce carbon emissions  and decrease energy consumption across the department.

Project Timeline

The construction phase is scheduled to begin in January 2025 and is expected to be completed by May 2027.

Project Cost and Funding

The total cost of the project is $6.6 million. It is funded primarily through an inter-county loan, which will be repaid over 15 years using energy savings. Given the 30-year lifespan of many improvements, the county anticipates significant additional savings after the loan is paid off.

Environmental Impact

The project is projected to reduce carbon dioxide emissions by approximately 530 metric tons per year which is equivalent to removing 106 cars from the road per year or offsetting the yearly use by 88 homes each year.

Energy Savings

Energy consumption at arenas is expected to decrease by about 25% annually due to the project’s upgrades and improvements. The implementation of this project will also reduce propane consumption by roughly 6% across the arena system.

The project includes a series of impactful upgrades:
 

Solar Energy Installations

LED Lighting Upgrades

Building Management Systems

Carbon and Energy Management Software

Mechanical System Upgrades

Building Envelope Improvements

This project represents a commitment to providing a better visitor experience across our facilities in a fiscally responsible and environmentally friendly way.

Construction is scheduled to commence  January 2025 and expected to wrap up May 2026. Updates will be shared as the project is implemented, so keep an eye out for the latest developments. Together, we’re building a more sustainable future for Ramsey County!