Ramsey County and the Minnesota Department of Transportation (MnDOT) track workforce hours and contracting on the Dale Street project. Figures will be updated on a monthly basis at this site.

Ramsey County Public Works is leading the project; Redstone Construction is serving as the primary contractor. 

Project goals and progress to date

Through July 14, 2021

View the full July 2021 report (PDF)

Total project completion

  • Budget paid (certified work) to the prime contractor (Redstone Construction) as of July 14: $11,067,925.10 of $11,790,010.45 (93.9%)

Disadvantaged business enterprise (DBE)

Read about DBE on the MnDOT website

  • Federal and county goal: 9.5%
  • Redstone Construction project commitment: 10.2%, or $1,208,323.57
  • Paid to DBEs to date (July 14): Redstone has paid $1,048,690.96 to DBEs (86.8% of total DBE commitment), 9.5% of the $11,067,925.10 that Redstone has been paid.

Workforce goals

  • County goal for all construction projects: 32% people of color and 20% women
  • Federal goal: 2.9% people of color and 6.9% women
  • Redstone Construction workforce plan: 11.5% people of color and 5% women
  • Project hours to date (July 10): 12.5% people of color and 6.8% women

On-the-job training

  • Federal requirement: five trainees and 2,000 hours
  • To date (July 10): five trainees have worked 2,194 total hours